T20240112.0055 | Albany Data Centre Generator Load Test
Scheduled Maintenance Report for PlanB
Completed
The scheduled maintenance has been completed.
Posted Jan 27, 2024 - 14:01 NZDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jan 27, 2024 - 10:00 NZDT
Scheduled
Plan B will be conducting Albany Data Centre generator load test. It is not envisaged that this test will affect customers, as the generator will supply power requirements during the test. Should the generator fail during the test period, UPS power will be provided while mains power is immediately restored.
Posted Jan 19, 2024 - 14:26 NZDT
This scheduled maintenance affected: Data Centers (Albany Data Centre (ALDC)).