10695 - SGS Data Centre UPS Upgrade

Scheduled Maintenance Report for PlanB

Completed

The scheduled maintenance has been completed.
Posted Aug 07, 2022 - 18:11 NZST

Update

Please be advised that SGS Data Centre UPS Upgrade has been completed successfully.
Posted Aug 07, 2022 - 18:11 NZST

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Aug 07, 2022 - 09:00 NZST

Update

We will be undergoing scheduled maintenance during this time.
Posted Jul 28, 2022 - 11:18 NZST

Scheduled

Plan B will be conducting the replacement of one of the SGS Data Centre UPS’s to ensure reliable operations. It is not envisaged that this upgrade work will affect customers.

All dual fed IT load will be protected by the sister UPS while the replacement is carried out. All IT devices will be additionally protected by the generator for the duration of the change.
Posted Jul 28, 2022 - 11:17 NZST
This scheduled maintenance affected: Data Centers (Christchurch SGS Data Centre).