T20240112.0052 | SGS Data Centre Generator Load Test
Scheduled Maintenance Report for PlanB
Completed
The scheduled maintenance has been completed.
Posted Jan 21, 2024 - 13:00 NZDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jan 21, 2024 - 09:00 NZDT
Update
We will be undergoing scheduled maintenance during this time.
Posted Jan 15, 2024 - 15:11 NZDT
Scheduled
Plan B will be conducting a generator load test at the SGS data centre. It is not envisaged that this test will affect customers, as the generator will supply power requirements during the test. Should the generator fail during the test period, UPS power will be provided while mains power is immediately restored.
Posted Jan 15, 2024 - 15:02 NZDT
This scheduled maintenance affected: Backup Platforms (Online Backup (CommVault) - Fully Managed Backups, Online Snapshot Platform - Fully managed Shadow Protect backups, Veeam Cloud Connect (VCC) - Off Site Repository For Veeam Backups, Server Replication (DoubleTake) Platform) and Data Centers (Christchurch SGS Data Centre).