Planned Maintenance | T20240724.0084 | Tawa DC Generator load test - 03 August 2024

Scheduled Maintenance Report for PlanB

Completed

The scheduled maintenance has been completed.
Posted Aug 03, 2024 - 12:00 NZST

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Aug 03, 2024 - 08:00 NZST

Scheduled

Plan B will be conducting the Tawa Data Centre generator load test. It is not envisaged that this test will affect customers, as the generator will supply power requirements during the test. Should the generator fail during the test period, UPS power will be provided while mains power is immediately restored
Posted Jul 26, 2024 - 16:58 NZST
This scheduled maintenance affected: Data Centers (Tawa Data Centre).